Inspections for New Construction Form

  1. All underground work – before backfill (i.e. water, sewer, storm traps).
    CALL FOR INSPECTION
  2. Site preparation and placing footing forms.
    CALL FOR INSPECTION
  3. Placement of wall forms and required re enforcement.
    CALL FOR INSPECTION
  4. Set drains, cover with gravel, apply damp proofing and foundation insulation.
    CALL FOR INSPECTION
  5. Complete rough framing, plumbing, electrical, and mechanical.
    CALL FOR INSPECTION
    NOTE: After rough plumbing inspection, make water deposit and set water meter.
  6. Install insulation AFTER APPROVAL OF ROUGH INSPECTIONS.
    CALL FOR INSPECTION
  7. Apply drywall only.
    CALL FOR INSPECTION PRIOR TO TAPING
  8. Provide certificate of Final Grade Elevation by registered Land Surveyor.
  9. Complete final and finishing work for structure, building, electrical, plumbing, and mechanical.
    CALL FOR INSPECTION
  10. Receive CERTIFICATE OF OCCUPANCY.